The written contract rule
ORS 701.305 requires a written contract when the aggregate price of work on a residential structure exceeds $2,000. If a job starts below that number and grows past it, the contractor must deliver a written contract within five days of knowing or reasonably knowing the price will exceed the threshold. The statute adds that failing to have a written contract does not void the contract, so an oral deal is still enforceable, but you will have a harder time proving what was promised. Do not use that as a reason to skip the paper.
What to include
Under CCB rules a residential contract must state the contractor's name, address, phone number and CCB licence number as shown in CCB records; your name and the address of the work; a description of the work, the price and the payment terms; your rights under the contract, including the right to file a complaint with the CCB; and whether there is a mediation or arbitration clause. Beyond those minimums, ask for:
- The contractor's name, address and CCB licence number, matching the CCB record.
- A detailed scope: materials by brand and grade, dimensions, finishes, demolition and disposal.
- The price, allowances and how change orders are priced and approved in writing.
- Payment schedule tied to completed milestones.
- Start date, target completion date and what happens with delays.
- Who pulls permits and schedules inspections.
- Warranty terms in writing.
- A clause on how disputes are handled. Under ORS 701.315 the contract may require mediation or arbitration, but may not limit your right to complain to the CCB.
The CCB's consumer tools page has its own list of what a well-written contract covers, including a list of allowance items with budgeted amounts and the permits each party is responsible for.
Notices you should receive
When a residential contract exceeds $2,000, the contractor must give you three notices and keep proof that you received them for two years: the Information Notice to Owner About Construction Liens, the Consumer Protection Notice and the Notice of Procedure. They may be printed inside the contract, signed separately, or acknowledged by your initials in the contract. The lien notice is required by ORS 87.093 and explains how to avoid paying twice for the same materials and labour. If you build a new home, the contractor must also offer a written warranty (ORS 701.320) and give you a recommended maintenance schedule covering moisture and water damage (ORS 701.335).
The CCB notes that a contractor who fails to provide a written contract and the required notices may lose the ability to claim a lien. Read the notices rather than signing past them; they are short.
Your right to cancel
Under ORS 701.310 you may cancel an initial written contract for work on your home by delivering written notice, including by email, before midnight at the end of the next business day. That right does not apply if you both agreed that work would begin sooner, once the contractor has substantially begun the work, or to later changes to the contract. Separately, when a contractor solicits you in person and you accept anywhere other than the contractor's permanent place of business, Oregon's home solicitation law (ORS 83.720) gives you until midnight of the third business day after signing or paying to cancel. The CCB says this applies to remodels and repairs, not the construction of a new house.
Paying safely
Avoid paying large sums up front. A modest deposit and payments after completed stages leave you leverage. Keep the final payment until the work is finished, inspected and any punch-list items are done. Pay by traceable methods and keep receipts. The CCB advises never paying the full amount up front, not paying in cash, and writing cheques to the business name on your contract.
Liens
Oregon's construction lien law lets suppliers and subcontractors who are not paid record a lien on the property, even if you paid your contractor. Ask for lien waivers or releases when you make payments, and read the construction lien information notice a contractor gives you for residential work. If the project is large, an attorney or title company can explain how to protect yourself.
Two details in chapter 87 help you track the risk. A supplier or subcontractor working for your contractor must send you a notice of right to a lien, and it protects only materials and labour supplied from eight business days before the notice was delivered or mailed (ORS 87.021). Keep every such notice, because it tells you who else expects to be paid. A lien must then be recorded with the county within 75 days after the claimant stopped work or after construction was completed, whichever is earlier (ORS 87.035).
Permits
Structural work generally needs a building permit from your city or county, and electrical and plumbing work needs permits and licensed trades. Ask who is pulling each permit, and keep inspection sign-offs with your house records.
Older homes and lead paint
The EPA's Renovation, Repair and Painting rule applies to most work that disturbs paint in homes built before 1978. Firms doing that work must be certified, and in Oregon the CCB issues a lead-based paint renovation contractor licence. If your house is older, ask the contractor whether they hold it, and how they will contain dust and clean up.
Before the first payment
- Check the licence on the CCB site.
- Check that the endorsement covers your kind of work.
- Get at least three written bids on the same scope.
- Read the contract twice and ask about anything vague.
General information only, current as of the date above. The information on Oregon Contractor Check is not a recommendation or a guarantee of anyone's work. A license record shows registration status on the date shown, not workmanship, insurance coverage at the time of your job, or suitability for your project. Confirm license, insurance and permits directly before you hire. Rules and programs change; check the official sources linked in this guide.